Australian Government Architecture
Search

Project closure reporting standard for digital and ICT-enabled projects

Introduction

Project closure reports provide visibility of how digital and ICT-enabled projects are performing in realising the scope and benefits as agreed and funded by government.

Project closure reports also provide the opportunity to:

  • acknowledge project achievements and outcomes
  • better prepare agencies to deliver future digital projects by capturing the successes and failures of a completed project
  • record key lessons which could improve the performance of other in-flight and future projects. 

This standard aims to:

  • guide closure reporting practices
  • ensure closure reports for Australian Government digital and ICT-enabled projects consistently include a minimum set of information.

How to use this Standard

Agencies should self-assess their draft project closure reports against each of the below criteria. 

Agencies should aim to be strongly aligned with all 7 criteria prior to finalising their project closure reports. The table below provides guidance on how to achieve this.

Agencies may use their own closure report templates or use the project closure reporting templates that have been developed by the DTA to align to the Standard.

Criteria

  1. The project has recorded project performance against the agreed scope outlined in the Business Case (or equivalent).
  2. The project has recorded project performance against the agreed schedule outlined in the Business Case (or equivalent).
  3. The project has recorded achievement of outcomes and measured benefits realisation against their benefits management plan.
  4. The project has recorded project performance against the agreed budget outlined in the Business Case (or equivalent).
  5. The project has recorded the completion of assurance activities as per the agreed Assurance Plan with the DTA.
  6. The project has detailed fit-for-purpose transition arrangements in preparation for a shift to a business-as-usual environment.
  7. The project has documented key lessons learned and how the lessons will be applied to in-flight and future projects for the agency and the Australian Government.

Criterion 1

The project has recorded project performance against the agreed project scope outlined in the Business Case (or equivalent).
Strong

The project closure report meets the Emerging requirements.

AND

Includes rationale for and subsequent impact of any adjustments to the agreed scope throughout the course of the project.

Emerging

The project closure report provides an overview of the project, its key objectives and scope components as agreed in the Business Case (or equivalent). 
A record of project performance against this scope is provided.

AND

Includes a record of any adjustments to the agreed scope throughout the course of the project.

AND

A copy of the original Business Case (as agreed by Government) and/or the project scope document is attached.

Nil The project closure report does not outline, or include artefacts that outline, an overview of the project and its scope as agreed in the Business Case (or equivalent). A record of project performance against this scope is not provided.

Criterion 2

The project has recorded project performance against the agreed project schedule outlined in the Business Case (or equivalent).
Strong

The project closure report meets the emerging requirements.

AND

Includes rationale for and the subsequent impact of any changes to the agreed schedule (including schedule slippages, movement of key milestones, or schedule change requests) throughout the course of the project.

Emerging The project closure report provides a record of project performance against the agreed schedule including the delivery of key milestones.
Nil The project closure report does not record project performance against the agreed schedule including the delivery of key milestones.

Criterion 3

The project has recorded achievement of outcomes and measured benefits realisation against their benefits management plan.
Strong

The project closure report meets emerging requirements.

AND

Includes an agreed plan for the full transition of ongoing benefit management and monitoring activities (e.g. governance arrangements) to benefit owners post project closure.

Emerging

The project closure report details the project’s achievement of outcomes and their relationship to benefits realisation as outlined in the benefits management plan. This includes the progress and percentage of benefits realised, expected date of realisation and transition of benefit owners.

AND

Includes a summary of and rationale for any formal changes to benefits and their realisation throughout the course of the project.

Nil The project closure report does not detail achievement of outcomes and their relationship to benefits realisation as outlined in the benefits management plan.

Criterion 4

The project has recorded project performance against the agreed budget outlined in the Business Case (or equivalent).
Strong

The project closure report meets the emerging requirements.

AND

Includes rationale for and subsequent impacts (including impacts to wider Agency) of any changes to the original budget (such as Movement of Funds requests or additional funding received).

Emerging

The project closure report provides a final budget position against the agreed budget and a breakdown of the project’s performance against this budget is included.

AND

Includes a record of any changes to the agreed budget throughout the course of the project.

Nil The project closure report does not provide the project’s final budget position or record of project performance against the agreed budget.

Criterion 5

The project has recorded the completion of assurance activities as per the agreed Assurance Plan with the DTA.
Strong

The project closure report meets emerging requirements.

AND

Includes an assessment of the effectiveness and value of assurance activities in achieving successful delivery of program outcomes.

Emerging

The project closure report records the completion of Assurance activities (this includes both internal and external Assurance activities) as per the agreed Assurance Plan with the DTA.

AND

Includes rationale for any material changes to planned assurance activities and a record of key outcomes from the assurance activities.

Nil The project closure report does not record the completion of Assurance activities as per the agreed Assurance Plan with the DTA.

Criterion 6

The project has detailed fit-for-purpose arrangements to transition to Business as Usual (BAU).
Strong

The project closure report meets the emerging requirements.

AND

The project closure report details the project’s sustainment funding plans and the impact of transferring incomplete or outstanding deliverables to BAU (if any).

Emerging

The project closure report details transition arrangements for the project and outlines the arrangements, delivery and responsible owners of any deliverables or scope components that remain incomplete or outstanding.

AND

The project closure report includes a register of key ongoing risks and issues that will be transferred to BAU.

Nil The project closure report does not detail transition arrangements for the project (including ongoing risks and issues) and does not acknowledge outstanding scope components.

Criterion 7

The project has documented lessons learned and how the lessons will be applied to in-flight and future projects for the agency and the Australian Government.
Strong

The project closure report meets the emerging requirements.

AND

The project closure report articulates how the key lessons identified are linked to the key delivery challenges and/or issues experienced throughout the course of the project; this includes addressing the source of each issue.

Emerging

The project closure report has documented key lessons from the project (including key learnings from the assurance activities) and the process through which they were identified (e.g. consultation with key internal and external stakeholders).

An explanation as to how the identified lessons will be applied to other in-flight and future projects has been included and artefacts that clearly outline full lessons learned, such as a lessons learned register, has been attached.

Nil The project closure report has not identified key lessons from the project, the process through which they were identified or provided an explanation as to how these lessons will be applied to other in-flight and future projects. Lessons learned artefacts including a lessons learned register have not been attached.

Capabilities

This standard supports digital solutions in the following capability.
CAP2

Benefits management

Policies

This standard assists in meeting the requirements of the following policies.
POL32

Benefits Management Policy

Designs

The following designs show how to achieve the intent of this standard.
​​Use the digital project closure report templates to meet the Project closure reporting standard for digital and ICT-enabled projects. The DTA has developed digital project closure report templates in collaboration with the Australian Taxation Office.
Was this information helpful?

Do not include any personal information. We are unable to respond to comments or feedback. If you would like a response, please email, or phone us. Our details are on the AGA contact page www.architecture.digital.gov.au/contact-us.